UP Cabinet Approves ₹3,706 Cr HCL-Foxconn Semiconductor Project

UP Cabinet Approves ₹3,706 Cr HCL-Foxconn Semiconductor Project
Contact Counsellor

UP Cabinet Approves ₹3,706 Cr HCL-Foxconn Semiconductor Project

AspectDetails
Project ApprovalApproved by the Uttar Pradesh Cabinet
Investing Companies1. Vamasundari Investments (HCL Group) with Foxcollaboration. 2. Tarq Semiconductor (Hiranandani Group).
Investment* Vamasundari (HCL Group): ₹3,706 crore. * Tarq Semiconductor: ₹28,440 crore.
LocationSector 10 and Sector 28 along the Yamuna Expressway, near Noida International Airport
Production FocusSmall panel driver ICs, display driver integrated circuits (DDIC)
Annual Output240,000 units (HCL Group's facility)
Employment Potential* Direct Employment: 1,000 jobs. * Indirect Employment: 10,000 jobs. * Additional Jobs: 3,780 (HCL Group).
Joint Venture DetailsVamasundari Investments (HCL Group) collaborates with Foxconn Hon Hai Technology India Mega Development for an OSAT facility.
Ownership Structure* Vamasundari Investments (HCL):60%. Foxconn:40%.
Land Allotment50 acres allocated by Yamuna Expressway Industrial Development Authority (YEIDA)
Infrastructure Needs* Electricity: 9,000 KVA. * Water: 2,000 MLD per day (85% recycling efficiency).
Government SupportState incentives and central government support under the India Semiconductor Mission (ISM) scheme
Timeline* Construction commencement: April 2024. * Operations start: Within 18 months of construction.
Strategic ImpactStrengthens India's semiconductor ecosystem, reduces import dependency, enhances UP's high-tech industry infrastructure.